2025 Highway 4 Projects
Hwy 4 Pacific Rim Base Repair
Timeline
August – Mid September.
Duration
4 – 6 weeks.
Traffic Impacts
Single Lane Alternating Traffic 24h/day Up to 20 minute delays.
Hydro Hill Base Repair
Timeline
July – November.
Duration
4 months.
Traffic Impacts
Single Lane Alternating Traffic 24h/day from July 5th - September 25th. Single Lane Alternating Traffic daytime only from September 26th - October 24th. Up to 30 minute delays.
Taylor River Area & Base Repairs and Resurfacing
Timeline
September – December.
Duration
4 months.
Traffic Impacts
Single Lane Alternating Traffic 24h/day Up to 20 minute delays.